ADMA-OPCO Accommodation and Administration Complex

Project Description

As part of Satah al-Razboot (SARB) Oilfield Development on Zirku Island, about 200 km north-west of Abu Dhabi, the project involves the detailed design of the accommodation and administration complex for Abu Dhabi Marine Operating Company (ADMA-OPCO).

The complex includes an administration building, an accommodation building, a fire station, a recreational building, an ablution building and a mosque, in addition to other facilities comprising electric substations and services utilities.

Accommodation Building:

With a built-up area of 9,500 m2, the building comprises a ground floor and 3 floors with an open-air courtyard.The building shall accommodate 254 residents in single occupancy rooms.The ground floor will accommodate common facilities and administrative functions.

Administration Building:

With a built-up area of approximately 5,400 m2, the blast- resistant building consists of a ground floor and two floors comprising offices, meeting rooms, 150-person auditorium, praying room & ablution area.

The sky lit full-height atrium provides natural lighting and reduces energy consumption.

Fire Station:

With a total built-up area of approximately 5,625 m2, the blast-resistant building comprises ground and first floors, lower roof and upper roof, in addition to a covered parking area for fire vehicles.

  • The ground floor comprises administration offices, lockers, a kitchen, a dining room, laundry and prayer rooms.
  • The first floor comprises 47 accommodation rooms, a linen room, storage rooms, a pantry and a lounge.
  • The lower roof floor comprises AHU rooms, toilets and a lobby.
  • The upper roof floor includes an Emergency Control Room (ECR).

Recreation Building:

With a total area of 600 m2, the building includes a gymnasium, a foyer, toilets and a squash court, in addition to an external football field and tennis court.

Ablution Building & Mosque:

With a total area of 135 m2, the ablution building consists of an ablution area, a foyer, bathrooms, in addition to a hand washing area.

With a total built-up area of 925 m2, the mosque accommodates 800 persons.

Activities

  • Architectural
  • Civil Works
  • Communications and security systems
  • Electrical
  • HVAC
  • Interior Design
  • Mechanical
  • Roads
  • Structural

Scope

  • Detailed design
  • Preliminary design

Client

Al Geemi and Partners Contracting Co.

LOCATION

abu-dhabi

,

project sheet

Download File (pdf 233KB)