33/13.8 KV Substations in NEOM

Project Description

The project entails the design and construction of 5 secondary substations (33kV/13.8), which are fed by the 132kV/33kV primary substations (PSSs). These substations distribute power from the 33kV power lines to the 13.8kV power lines, ensuring reliable and stable transfer of power to downstream loads, including commercial, residential, and industrial areas within Oxagon sitewide.
To ensure the reliability and stability of the power supply, redundancies are integrated into the design of the infrastructure, utility network, and assets. In addition, essential components of the distribution system, such as MV/MV and MV/LV transformers, MV switchgears, and the MV cable network, are installed within the MV/MV secondary substations, providing power to assets and the field.
The substation building is a prototype spanning a 2,500 m2 plot with a total built-up area of 727 m2. The five substations are strategically positioned across five site layouts to enhance infrastructure redundancy and ensure network reliability.

Activities

  • Architectural
  • Communications and security systems
  • Electrical
  • HVAC
  • Infrastructure
  • Landscaping
  • Mechanical
  • Roads
  • SCADA
  • Structural

Scope

  • Detailed design
  • Design development
  • Shop drawings
  • As-Built Drawings

Client